How Long Does an MOT Bay Project Take?

MOT Expert Ashley Hance
Ashley Hance MSc – Director of GETECH and MOT Project Expert

Our own MOT Expert Ashley Hance talks through MOT timings in this blog article…

“Often I am asked at the point of sale as to the likely lead-time for the introduction of an MOT bay into an existing or new business premises…

It is a question which is difficult to accurately answer given the complexity of an MOT bay project but personally I always like to work on a worst case scenario – things only ever improve from there!

The long lead time item within the application process is without doubt the “local authority consent” aspect. More often that not, local Council records of the premises are either non-existent or unhelpful. Furthermore the planning department will often state that they do not necessarily know the exact usage ongoing within the premises – in essence they are looking at historical information. Although this may seem a little strange to the layman, it does make sense; planning and enforcement are tasked with planning and enforcement so if no application for planning has been made, or if you have had no complaints raised by enforcement then  despite the fact that you are probably banded correctly for your business rates by the Council’s own business rates people – the planning department may have no knowledge of the activities being conducted within the premises.

You can also be assured that local authorities have become more greatly skilled at pushing unsuspecting applicants towards a planning application of some kind; be it full planning, change of use or a lawful development certificate. After all funds in the public sector are non-existent and if you cannot prove that the usage is legal and that the proposed changes also fall within that legal framework then inevitably you will be forced into a cost, and more undesirably, a 8 week delay in starting the application process to the DVSA.

So how can you avoid this requirement? The truth is that from a DVSA perspective you cannot. The VT01 clerks are looking for something from the local authority in question which states that either planning is not required, the MOT Bay will be covered within existing planning permissions or that permission has been granted for the MOT bay as a result of a planning application.

How do you achieve planning approval? Well you can speak to the Council yourself and attempt to navigate your way through planning law for what will probably be the first and last time – or alternatively you can pick up the phone to GETECH Garage Equipment and be guided through the entire process from start to finish with the minimum of direct involvement.

Complete planning applications including floor-plan and elevation drawings, flood risk assessments, traffic flow studies and more can all be supplied or project managed by GETECH where there is a specific requirement from a Council’s planning department.

Even if you are not an existing customer of GETECH, we can still be employed to conduct this aspect of your project on your behalf – you could even get a better deal on your equipment by speaking to us and cutting out the distributor network altogether!

Visit our “Other Services” page by clicking this link and find out how much more than just a garage equipment manufacturer GETECH actually is…

Coming back to the question though…

…once the planning (if applicable is achieved) the rest of the application and realisation process is fairly straightforward. DVSA approval can, in 2017, ordinarily be achieved within a week of submission – and with no site visits required by the DVSA until the bay is ready to be signed off, you could genuinely be into your groundwork and electrical preparation stages promptly. Installation only takes a day or so (dependent on the type of bay you have opted for), as does the approval of the Ministry…

Therefore in a tightly managed project where no planning is required – a lead time of approximately 3-8 weeks is achievable (irrespective of what class of vehicle will be tested). Whereas with a planning application requirement you could be looking at a lead time of 11-16 weeks from start to finish.

If you have been informed that the application process takes a ling time and it is difficult to obtain a prompt approval (I have heard horror stories of 6-9 months on my travels around the UK) – you are definitely talking to the wrong supplier! Our “can-do” attitude will see you authorised within the lead times indicated above!


For more information on GETECH call during office hours, visit http://getech.org.uk or mail info@getech.org.uk.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s